← Back to mapAusbaustrecke
Feste Fehmarnbeltquerung (Hinterlandanbindung)
Under Construction- Length
- 88 km
- Max Speed
- 200 km/h
- Cost
- 3.5 bn EUR
- Responsible
- DB InfraGO AG
- Corridor
- Hamburg–Kopenhagen
Travel Time Impact
Hamburg Hbf → Puttgarden
Before
143 min
After
75 min
Timeline
Sept. 2008
Project StartTarget completion: Dez. 2028Jan. 2019
PlanfeststellungTarget completion: Dez. 2029Planfeststellungsbeschluss für mehrere AbschnitteJan. 2021
Construction StartTarget completion: Dez. 2029Dez. 2029 (projected)
CompletedTarget completion: Dez. 2029The German rail hinterland connection for the Fehmarnbelt Fixed Link tunnel between Germany and Denmark. The project upgrades and electrifies 88 km of rail between Lübeck and Puttgarden, including new double-track sections and station modifications. Together with the Danish tunnel, it will dramatically cut Hamburg–Copenhagen travel times.