Ausbau- und Neubaustrecke Karlsruhe–Basel

Under Construction
Ausbaustrecke
Length
182 km
Max Speed
250 km/h
Cost
12.0 bn EUR
Responsible
DB InfraGO AG
Corridor
Karlsruhe–Basel

Travel Time Impact

Karlsruhe HbfBasel Bad Bf

Before
80 min
After
55 min

Timeline

Jan. 1987
Project StartTarget completion: Dez. 2020
Juni 2003
Construction StartTarget completion: Dez. 2035
Juni 2004
Section CompletedRastatt Süd–Offenburg (4-gleisig)Target completion: Dez. 2020
Dez. 2020
Section CompletedKatzenbergtunnel (Efringen-Kirchen–Bad Bellingen)Target completion: Dez. 2041
Dez. 2041 (projected)
CompletedTarget completion: Dez. 2041Full 4-track expansion with Rastatt Tunnel

Germany's longest ongoing rail infrastructure project: a full four-track expansion of the Upper Rhine corridor between Karlsruhe and Basel, a key bottleneck on the Rotterdam–Genoa freight corridor. The project includes the 4.3 km Katzenbergtunnel (completed 2012) and the critical Rastatt Tunnel section. Completion of all sections is expected around 2041.

Last updated: 2025-04-01