Neubaustrecke Dresden–Prag (Erzgebirgstunnel)
Planned- Length
- 43 km
- Max Speed
- 200 km/h
- Responsible
- DB InfraGO AG
- Corridor
- Dresden–Prag
Travel Time Impact
Dresden Hbf → Praha hl.n.
Before
135 min
After
60 min
Timeline
Jan. 2015
Project StartTarget completion: Dez. 2040Dez. 2030 (projected)
Route SelectedTarget completion: Dez. 2045A cross-border new-build line between Dresden and Prague, centred on a roughly 25 km base tunnel through the Erzgebirge (Ore Mountains). The project would halve the Dresden–Prague travel time and establish a competitive rail connection between central Germany and the Czech Republic. Currently in early planning with joint German-Czech feasibility studies.