← Back to mapAusbaustrecke
Ausbaustrecke München–Lindau (Elektrifizierung)
Completed- Length
- 155 km
- Max Speed
- 160 km/h
- Cost
- 0.5 bn EUR
- Responsible
- DB InfraGO AG
- Corridor
- München–Lindau
Travel Time Impact
München Hbf → Lindau Hbf
Before
162 min
After
118 min
Timeline
Jan. 2010
Project StartTarget completion: Dez. 2020März 2018
Construction StartTarget completion: Dez. 2021Dez. 2021
CompletedElectrification of the Munich–Lindau line, enabling through-running of electric trains to Bregenz, Zurich, and the Austrian Vorarlberg without locomotive changes. The project included 155 km of new catenary, platform modifications, and signal upgrades. Completed in December 2021.
Official Links
Last updated: 2025-04-01