Ausbaustrecke München–Lindau (Elektrifizierung)

Completed
Ausbaustrecke
Length
155 km
Max Speed
160 km/h
Cost
0.5 bn EUR
Responsible
DB InfraGO AG
Corridor
München–Lindau

Travel Time Impact

München HbfLindau Hbf

Before
162 min
After
118 min

Timeline

Jan. 2010
Project StartTarget completion: Dez. 2020
März 2018
Construction StartTarget completion: Dez. 2021
Dez. 2021
Completed

Electrification of the Munich–Lindau line, enabling through-running of electric trains to Bregenz, Zurich, and the Austrian Vorarlberg without locomotive changes. The project included 155 km of new catenary, platform modifications, and signal upgrades. Completed in December 2021.