2. S-Bahn-Stammstrecke München

Under Construction
Knoten
Length
10 km
Max Speed
80 km/h
Cost
7.2 bn EUR
Responsible
DB InfraGO AG
Corridor
München S-Bahn

Timeline

Jan. 2001
Project StartTarget completion: Dez. 2015
Juni 2015
PlanfeststellungTarget completion: Dez. 2026
Apr. 2017
Construction StartTarget completion: Dez. 2028
Dez. 2037 (projected)
CompletedTarget completion: Dez. 2037Completion delayed significantly from original 2028 target

A second trunk line for Munich's S-Bahn network, running 10 km underground through the city centre with three new stations. The project addresses chronic capacity bottlenecks on the existing single-trunk S-Bahn system. Originally planned for completion by 2028, the timeline has been repeatedly pushed back due to geological challenges and cost increases.

Last updated: 2025-04-01